August 15, 2016
The Rapid Bridge Replacement Project will begin in Lawrence County with the start of construction on a bridge beginning in late August.
The Neshannock Fall Road (SR 1009) over the Branch of Neshannock Creek in Wilmington Township (JV-474) is scheduled to close August 29, 2016. Traffic will be detoured using Eastbrook Volant Road (SR 0168) to PA 956.
Construction of the bridge will take approximately ten weeks to complete. The bridge was built in 1913 and averages 161 vehicles a day.