January 25, 2017
Construction for the Route 18 (Golden Oaks Road) bridge, spanning House Run in Center Township, Greene County, is scheduled to begin as part of the Pennsylvania Department of Transportation’s (PennDOT) Rapid Bridge Replacement Project. Replacement of this bridge will allow PennDOT to remove it from Greene County’s structurally deficient list.
Construction is expected to begin during the week of February 6 and be complete in late July. During this time, alternating bi-directional traffic will be controlled by traffic signals.
In the event of unfavorable weather or unforeseen activities, this schedule may change.
This bridge is referred to as JV-504 and is one of 558 bridges being replaced under the Rapid Bridge Replacement Project. JV references the joint-venture partnership between Walsh/Granite, which is leading construction for the entire project.
Media contact: Plenary Walsh Keystone Partners: Jeff Rossi, 412-569-1832.