Construction To Begin on Lawrence County Bridge Project - Frew Mill Road

See below for more information on the Rapid Bridge Replacement Project

  • Who Is Walsh Group, Plenary Group, Granite & HDR?
  • What Is The Rapid Bridge Replacement Project?


June 28, 2016

The Rapid Bridge Replacement Project continues in Lawrence County with the start of reconstruction on a bridge beginning in July.

The Frew Mill Road crossing over Big Run in Slippery Rock (JV-475) is scheduled to close July 5. Traffic will be detoured using SR 388 to SR 422 to SR 2013 (Mount Herman Church Road). Construction of the bridge is expected to be completed by mid-September. The bridge was built in 1940 and averages 860 vehicles a day.


facebook Email Twitter YouTube 511pa

About The ProjectContact Us

4 Penn Center Blvd., Suite 100
Pittsburgh, PA 15275

info@parapidbridges.com

Hotline: 877-444-9990
Hours: M–F from 8:30 a.m. – 5 p.m. ET

Contact:  Andrew Dressler,  312.756.9119

Plenary Walsh Keystone Partners believes in engaging local community and disadvantaged business enterprise (DBE) resources to benefit our projects and the communities in which we do business. We seek to establish relationships with local DBE firms, encourage and assist potential DBEs to obtain necessary certification and prequalification, and aid development of DBEs through their active involvement.

View Available Jobs    An Equal Opportunity Employer, Disability/Veteran.

Copyright © 2019 Plenary Group | Walsh Group | Granite | HDR. All rights reserved.

Plenary GroupWalsh GroupGraniteHDR